ID: Q132092
The information in this article applies to:
The DurationValue method in Microsoft Project is used to convert a duration value into the equivalent number of minutes. This conversion is always based on the current conversion defaults for the application, rather than the conversion defaults for a specific project.
A custom function can be used in place of DurationValue to return values based on project-specific conversion defaults.
The DurationValue method takes a duration value as a string argument and returns an integer number of minutes. If the duration value is specified in units of Days or Weeks, this conversion is based on the current application default values for Hours Per Day and Hours Per Week. For example, with the initial default value for Hours Per Day set to 8.00 using this value, 5d = 40h = 2400m; Application.DurationValue("5d") = 2400.
Changing the Hours Per Day setting for a specific project does not affect this calculation. For example, making the following change will not affect this calculation:
1. On the Tools menu, click Options.
2. Select the Calendar tab.
3. In the Hours Per Day box, type "7.00" (without the quotation marks), and
choose OK.
This procedure changes the Hours Per Day value for the current project
only. In this situation, Application.DurationValue still returns 2400
because this method operates at the application level not the project
level.
1. On the Tools menu, click Options.
2. Select the Calendar tab.
3. In the Hours Per Day box, type "7.00" (without the quotation marks).
4. Choose the Set as Default button.
5. Choose the OK button.
After you make this change, Application.DurationValue("5d") = 2100. (5d = 35h = 2100m)
It is also possible to create an equivalent function that returns the number of minutes based on the conversion settings in a particular project. The following example ProjDurationValue function takes a project object and a duration string as arguments, and returns the corresponding number of minutes for that duration.
Microsoft provides examples of Visual Basic procedures for illustration only, without warranty either expressed or implied, including but not limited to the implied warranties of merchantability and/or fitness for a particular purpose. This Visual Basic procedure is provided 'as is' and Microsoft does not guarantee that it can be used in all situations. Microsoft does not support modifications of this procedure to suit customer requirements for a particular purpose.
Function ProjDurationValue(oProj As Object, sDur As String) As Long
' This function returns the number of minutes equivalent
' to the passed duration based on conversion values in the
' passed project.
' ProjDurationValue returns -1 if an invalid duration value is passed.
' oProj = project whose conversion values we're using
' sDur = duration to convert
ProjDurationValue = -1 ' Return -1 if invalid duration
If InStr(sDur, "e") > 0 Then ' Elapsed duration
Select Case Right(sDur, 2)
Case "ed" ' Elapsed days
'1440 = number of minutes in 1 elapsed day
ProjDurationValue = Val(sDur) * 1440
Exit Function
Case "ew" ' Elapsed weeks
'10080 = number of minutes in 1 elapsed week
ProjDurationValue = Val(sDur) * 10080
Exit Function
End Select
End If
Select Case Right(sDur, 1)
Case "m" ' Minutes and Elapsed Minutes
ProjDurationValue = Val(sDur)
Case "h" ' Hours and Elapsed Hours
ProjDurationValue = Val(sDur) * 60
Case "d" ' Days
Temp = oProj.Duration1
oProj.Duration1 = "1d"
ProjDurationValue = Val(sDur) * 60 * (oProj.Duration1 / 60)
oProj.Duration1 = Temp
Case "w" ' Weeks
Temp = oProj.Duration1
oProj.Duration1 = "1w"
ProjDurationValue = Val(sDur) * 60 * (oProj.Duration1 / 60)
oProj.Duration1 = Temp
End Select
End Function
Additional query words: 4.00
Keywords : kbcode kbprg
Version : 4.0 4.1 98
Platform : MACINTOSH WINDOWS
Issue type : kbhowto