PRJ98: Microsoft Project Takes a Long Time to Save Baseline

ID: q173169


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, if you save a baseline it may take a long time and Project appears to stop responding (hang).


CAUSE

Microsoft Project may take a long time to save a baseline because it calculates a large amount of data to set baseline fields. When a baseline is saved, baseline values for all tasks are rolled up to summary tasks and all resource assignment information is rolled up to resource baseline fields. Microsoft Project now includes timescaled data associated with each task and each resource. This timescaled data includes a large amount of information, which causes significantly more calculations than previous versions.


STATUS

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1

Additional query words:


Keywords          : projwin 
Version           : WINDOWS:98
Platform          : WINDOWS 
Issue type        : kbbug 

Last Reviewed: July 23, 1999