PRJ98: Project Stops Responding When Resource DeletedID: q174358
|
In Microsoft Project 98, if you delete a resource in Resource Usage view, You may receive one of the following error messages.
If you click Details, you receive an error message similar to this:This program has performed an illegal operation and will be shut down. If the Problem persists, contact the program vendor.
WINPROJ caused an invalid page fault in module WINPROJ.EXE at <address>.
An Application Error has occurred and an application error log is being generated.
Winproj.exe
Exception access Violation (oxc0000005), Address:<address>
These errors occur if you delete a resource in Resource Usage view when baseline work has been assigned to the resource and baseline cost has not been calculated for the resource.
For example, these errors occur in the following situations:
To work around this problem, do not delete a resource from the Resource Usage view if baseline work has been assigned to a resource. Instead, delete the resource from the Resource Sheet view.
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words: ipf crash crashes crashing crashed quit quitting quits fail fails failing failed break
Keywords : kberrmsg kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 19, 1999