PRJ98: Incorrect Work Value in Usage Views for In-Progress TasksID: q175031
|
In Microsoft Project 98, the Task Usage and Resource Usage views may show incorrect Work and Actual Work values for some tasks and resources when the task is in progress.
This behavior occurs when the following conditions occur:
-and-
To work around this problem, change the project start date for the resource
pool so that it is the same as the project's sharing pool. To do this,
follow these steps:
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
When you make a calendar exception for a day of the week, you change the
default working time for that day. Microsoft Project will then determine if
a new default should be used for the day, by using the following criteria: