PRJ: Removing All Resources From Task Removes All WorkID: q178185
|
In Microsoft Project, if you remove all resources from a task, the Work
assigned to the task is also removed.
Although you might expect that a Fixed Work task would not lose assigned
work when a resource is removed, this behavior occurs for all types of
tasks: Fixed Work, Fixed Duration, and Fixed Units.
To work around this problem, reassign the value of Work to the task after removing all the task's resources.
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : projwin projmac
Version : MACINTOSH:4.0; WINDOWS:4.0,4.1,4.1a,98
Platform : MACINTOSH WINDOWS
Issue type : kbbug
Last Reviewed: July 16, 1999