SYMPTOMS

In Microsoft Project 98, some tasks in a project may display a split when a split is not expected.


CAUSE

This behavior occurs when you load a file created in Microsoft Project 4.O, and the task that displays the split has a percent complete greater than zero, is a fixed duration task, and has no resource assigned.


WORKAROUND

To work around this problem, change the duration of the task to zero. Then, reenter the original duration and percent complete.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1

Additional query words:


Keywords          : kbdta projwin 
Version           : WINDOWS:98
Platform          : WINDOWS 
Issue type        : kbbug 

Last Reviewed: July 15, 1999