PRJ98: Cost Field Value Is Less Than Expected ValueID: q180914
|
In Microsoft Project 98, you may find that the Cost field for one or more
tasks does not equal the sum of the costs assigned to it; for example,
given a task that is 50% complete and has a $10 fixed cost assigned:
Expected:
Day 1 Day 2 Day 3 Day 4
Cost $2.50 $2.50 $2.50 $2.50
Actual:
Day 1 Day 2 Day 3 Day 4
Cost $1.25 $1.25 $1.25 $1.25
This problem occurs when the option Actual costs are always calculated by Microsoft Project is turned off and a task's % Complete is greater than zero.
When you turn this option off, Microsoft Project will not automatically
increase actual costs. The Cost field is calculated following the equation:
Cost = Actual Cost + Remaining Cost. Because actual cost is not increased
when the % Complete is increased, the cost may seem incorrect.
To work around this problem, use either of the following methods:
-or-
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999