PRJ98: Additional Tasks, Links, Assignments When Pasting TasksID: q180923
|
In Microsoft Project 98, when you copy and paste a selection of tasks, you
may see any of the following symptoms:
This problem occurs when you copy tasks that include an inserted project
that is expanded.
In addition to pasting the inserted project as a whole, Microsoft Project
also pastes the tasks from the inserted project as individual tasks in the
consolidated project.
To work around this problem, collapse the inserted project before copying it. To do this, click the minus sign next to the inserted project's summary task. After you paste the selection of tasks, you can expand the inserted project if necessary.
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999