PRJ98: Summary Task Displays Incorrect Percent CompleteID: q183460
|
In Microsoft Project 98, when you change the percent complete for a task that is a subtask, the % Complete field for the summary task that contains the subtask may display an incorrect value.
To resolve this behavior, press F9 to have Microsoft Project recalculate the fields.
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999