PRJ98: Summary Task Displays Incorrect Percent Complete

ID: q183460


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, when you change the percent complete for a task that is a subtask, the % Complete field for the summary task that contains the subtask may display an incorrect value.


RESOLUTION

To resolve this behavior, press F9 to have Microsoft Project recalculate the fields.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1