PRJ98: Missing Tasks When Print or Print Preview Calendar ViewID: q184002
|
In Microsoft Project 98, when you print or print preview a project in the Calendar view, some tasks might not be displayed.
This behavior occurs when the following conditions are true:
To work around this behavior, move the task that was missing in the printout or in print preview to a different row in the Calendar view, by clicking it and dragging it up or down.
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbprint kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999