PRJ98: Copied Project Tasks Do Not Appear in Outlook Task List

ID: q184611


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, if you duplicate tasks that are assigned to a resource, the duplicated tasks may not appear in the resource's task list in Microsoft Outlook.


CAUSE

This behavior occurs when the following conditions are true:

Outlook incorrectly identifies the copied tasks as the same task that already exists in the task list.


WORKAROUND

To work around this behavior, do not duplicate an entire task, but only copy and paste selected fields into a new task but. If you select and copy the entire task, you will experience the symptoms described earlier.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1

Additional query words:


Keywords          : kbinterop kbdta projwin 
Version           : WINDOWS:98
Platform          : WINDOWS 
Issue type        : kbbug 

Last Reviewed: July 14, 1999