PRJ98: Copied Project Tasks Do Not Appear in Outlook Task ListID: q184611
|
In Microsoft Project 98, if you duplicate tasks that are assigned to a resource, the duplicated tasks may not appear in the resource's task list in Microsoft Outlook.
This behavior occurs when the following conditions are true:
-and-
-and-
To work around this behavior, do not duplicate an entire task, but only copy and paste selected fields into a new task but. If you select and copy the entire task, you will experience the symptoms described earlier.
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbinterop kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999