PRJ98: Periodic Resource Report Shows Incorrect TasksID: q184613
|
In Microsoft Project 98, when you print or print preview a resource report
that has the Period set to anything other than Entire Project, tasks may be
listed during incorrect periods and may also be incorrectly repeated.
NOTE: The period specifies the time units of the intervals for which
Microsoft Project prints information.
This behavior occurs when a resource report is set to show any period other than the entire project.
To work around this problem, select Entire Project as the Period. To set
this option, follow these steps:
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999