PRJ98: Unexpected Start, Finish, Hours Per Day or Hours Per WeekID: q184688
|
In Microsoft Project 98, when you open a project in the MPX format, default
working Hours Per Day or Hours Per Week may be an incorrect value.
In addition, the Start or Finish time for one or more tasks may be
incorrect.
This behavior occurs when the Hours Per Day or Hours Per Week of a project includes a decimal fraction value (such as 7.5), and you save the project in the MPX 4.0 file format, close it and then reopen it.
To work around this behavior, change the default Hours Per Day or Hours Per
Week to the correct value after opening the MPX file.
To do this, follow these steps:
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999