PRJ98: Missing Baseline or Earned Value Info in Usage View
ID: q184708
|
The information in this article applies to:
-
Microsoft Project 98 for Windows
SYMPTOMS
In Microsoft Project 98, in a project where a baseline has been saved, when
you view either the Task Usage or Resource Usage view, the following
timephased fields may be blank:
Baseline Work
Baseline Cost
Budgeted Cost of Work Schedules (BCWS)
Budgeted Cost of Work Performed (BCWP)
Cost Variance (CV)
Schedule Variance (SV)
CAUSE
This behavior occurs when you do the following:
- You change the Baseline Start or Baseline Finish field
for a task, without first viewing the fields listed in the "Symptoms"
section in either the Task Usage view or Resource Usage
view.
- You then save, close and then reopen the project.
When you view any of the timephased fields listed in the "Symptoms" section
in either of the Usage views, information is missing.
WORKAROUND
To work around this behavior, use the method appropriate for your
situation.
Method 1
If you have not saved and closed the project since you changed the Baseline
Start or Baseline Finish for the task, follow these steps:
- On the View menu, click Task Usage.
- On the Format menu, click Detail Styles and then click
the Usage Details tab.
- Under Available Fields, click Baseline Work and click
Show.
- Repeat step 3 for the following fields.
Baseline Cost
Budgeted Cost of Work Schedules (BCWS)
Budgeted Cost of Work Performed (BCWP)
Cost Variance (CV)
Schedule Variance (SV)
- Click OK after the fields in step 4 appear in the Show
These Fields list.
When you save the project, the behavior described in the "Symptoms" section
will not occur.
Method 2
If you have saved, closed and reopened your project since you changed the
Baseline Start or Baseline Finish, you must resave the baseline to restore
the timescaled values. To resave the baseline for the affected tasks,
follow these steps:
- Select all of the tasks that display the symptoms.
- On the Tools menu, point to Tracking, and click Save
Baseline.
- In the Save Baseline dialog box, click Save Baseline
and then click Selected Tasks. Click OK.
After saving the baseline, change the Baseline Start and/or Baseline Finish
to the appropriate day, and then follow method 1 above.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 14, 1999