PRJ98: Crash If Selecting Calendar in Change Working Time DialogID: q185877
|
In Microsoft Project 98, when you select a calendar in the Change Working Time dialog box, you may receive one of the following error messages.
When you click Details, you receive the following error:This program has performed an illegal operation and will be shut down.
If the problem persists, contact the program vendor.
WINPROJ caused an invalid page fault in module WINPROJ.EXE at <address>.
An application error has occurred and an application error log is being generated.
WINPROJ.EXE
Exception: access violation <number>, Address: <address>.
This behavior occurs in consolidated projects when you do the following in
the Change Working Time dialog box:
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
To work around this problem in Microsoft Project 98 (non SR-1), follow
these steps:
Microsoft has confirmed this to be a problem in the Microsoft products listed
at the beginning of this article.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kberrmsg kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 13, 1999