PRJ98: Work and Baseline Work Do Not Match After Saving Baseline

ID: q186071


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, after saving a baseline, when you view the Task Usage or Resource Usage view, timephased Baseline Work values might not be the same as timephased Work values.

NOTE: There may also be timephased Baseline Work values of zero after the task Finish date.


CAUSE

This problem may occur when all of the following conditions are true:


RESOLUTION

To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1).


STATUS

Microsoft has confirmed this to be a problem in the Microsoft products listed at the beginning of this article.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1