PRJ98: Work and Baseline Work Do Not Match After Saving BaselineID: q186071
|
In Microsoft Project 98, after saving a baseline, when you view the Task
Usage or Resource Usage view, timephased Baseline Work values might not be
the same as timephased Work values.
NOTE: There may also be timephased Baseline Work values of zero after the task Finish date.
This problem may occur when all of the following conditions are true:
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
Microsoft has confirmed this to be a problem in the Microsoft products listed
at the beginning of this article.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 13, 1999