Can't Resolve Overallocation If Leveling Minute-By-Minute

ID: q187372


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, when you level resources, some resource overallocations might not be resolved, nor do you receive any messages.

NOTE: If you do receive leveling messages, there may be other causes such as task constraints, task Actual Start dates, or task relationships that prevent the tasks from being leveled correctly.


CAUSE

This behavior may occur when leveling is set look for overallocations on a minute-by-minute basis.


RESOLUTION

To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1).


STATUS

Microsoft has confirmed this to be a problem in the Microsoft products listed at the beginning of this article.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1


MORE INFORMATION

For more information about resource leveling, click the Office Assistant, type "Resource Leveling," click Search, and then click to view "Resource Leveling."

NOTE: If the Assistant is hidden, click the Office Assistant button on the Standard toolbar. If Microsoft Help is not installed on your computer, please see the following article in the Microsoft Knowledge Base:

Q120802 Office: How to Add/Remove a Single Office Program or Component