PRJ98: Resources Printed with Incorrect Tasks in ReportID: q187390
|
In Microsoft Project 98, when you print or print preview a report, resources may be displayed with incorrect tasks.
This problem occurs when you print or print preview a report based on the
crosstab report, and either the Sort Resources By Project or the Keep
Outline Structure options are cleared.
NOTE: The Sort Resources By Project option is only available when the crosstab report Row is set to Resources. The Keep Outline Structure option is only available when the crosstab report Row is set to Tasks.
To confirm that your report is based on a Crosstab Report, follow these steps:
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
To work around this problem, turn on the Sort Resources By Project or Keep Outline Structure options. To do this, follow these steps:
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbprint kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 13, 1999