PRJ98: Leveling Week by Week Gives Unnecessary Delay and SplitsID: q188783
|
In Microsoft Project 98, when you use resource leveling, you may find unnecessary delays and splits for linked tasks.
This problem occurs when you use resource leveling in Microsoft Project 98 and "Look for overallocations on a 'Week by Week' basis" is selected in the Resource Leveling dialog box, and the task has a predecessor task.
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
After opening the project in Microsoft Project 98 SR-1, use resource
leveling on the project again. The unnecessary delay and splits will be
resolved correctly.
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1