PRJ98: Timephased Percent Complete Recalculated When EnteredID: q188799
|
In Microsoft Project 98, when you edit the timephased percent complete for a task in the Task Usage view, you may see a different value than you entered for the task.
This behavior is more likely to occur when the following conditions are
true:
To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1).
Microsoft has confirmed this to be a problem in the Microsoft products listed
at the beginning of this article.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
Q185102 PRJ98: How to Obtain and Install MS Project 98 SR-1
Additional query words:
Keywords : kbdta projwin
Version : WINDOWS:98
Platform : WINDOWS
Issue type : kbbug
Last Reviewed: July 12, 1999