PRJ98:Updated %Complete & BCWP All in First Period of Task UsageID: q189247
|
In Microsoft Project 98, when you update percent complete for a task, all percent complete values and BCWP values may appear in the first time period of the Task Usage view.
This behavior occurs when all of the following conditions are true:
To correct this behavior, install Microsoft Project 98 for Windows, Service Release 1 (SR-1).
Microsoft has confirmed this to be a problem in the Microsoft products listed
at the beginning of this article.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
Q185102 PRJ98: How to Obtain and Install MS Project 98 SR-1