PRJ98: Resource Peak Units May Be Displayed IncorrectlyID: q189878
|
In Microsoft Project 98, resource Peak Units may display incorrectly in a
resource view.
For example, time-phased resource Peak Units for a period may be blank even
though the resource has assignments for that period.
This behavior occurs when multiple assignments for a single resource for the same time period exceed the Microsoft Project limit of 10,000 units (1,000,000 per cent) for a single resource assignment.
To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1). Resource units will not be displayed incorrectly when multiple assignments for a single resource for the same time period exceed the Microsoft Project limit of 10,000 units (1,000,000 per cent) for a single resource assignment.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
Q185102 PRJ98: How to Obtain and Install MS Project 98 SR-1
If the sum of all assignments exceeds the 10,000 limit for any period, the time-phased resource Peak Units field for that period in the Resource Usage view will be blank, and the resource Peak field on a resource table will display as 1.