Date Subvector of NVAlert Major Vector Incorrectly Set in Year 2000

ID: Q196038


The information in this article applies to:


SYMPTOMS

The Date subvector of NVAlert major vector is set incorrectly when the date is changed to the year 2000.


RESOLUTION

To resolve this problem, obtain the latest service pack for SNA Server version 3.0. For additional information, please see the following article in the Microsoft Knowledge Base:

Q184307 How to Obtain the Latest SNA Server Version 3.0 Service Pack


STATUS

Microsoft has confirmed this to be a problem in Microsoft SNA Server versions 3.0, 3.0 Service Pack 1, 3.0 Service Pack 2, 3.0 Service Pack 3, 4.0, 4.0 Service Pack 1. This problem was first corrected in SNA Server 3.0 Service Pack 4.

Additional query words:


Keywords          : 
Version           : WinNT:3.0, 3.0 SP1, 3.0 SP2, SP3, 4.0, 4.0 SP1
Platform          : winnt 
Issue type        : kbbug 

Last Reviewed: July 8, 1999