PRJ98: Resource Time-Phased SV Does Not Equal Resource Total SV

ID: q178678


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, in the Resource Usage view, you may see that a resource time-phased Schedule Variance (SV) does not equal the total SV values for the resource.


CAUSE

This behavior occurs when the following conditions are true:

Resource time-phased SV values are using the rolled up assignments Budgeted Cost of Work Scheduled (BCWS) values instead of the resources BCWS values.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1


MORE INFORMATION

Additional query words: scheduled s v


Keywords          : projwin 
Version           : WINDOWS:98
Platform          : WINDOWS 
Issue type        : kbbug 

Last Reviewed: July 16, 1999