PRJ98: Missing Tasks When Print or Print Preview Calendar View

ID: q184002


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, when you print or print preview a project in the Calendar view, some tasks might not be displayed.


CAUSE

This behavior occurs when the following conditions are true:


WORKAROUND

To work around this behavior, move the task that was missing in the printout or in print preview to a different row in the Calendar view, by clicking it and dragging it up or down.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1