PRJ98: Unexpected Leveling Delay for Tasks with SNET Constraint

ID: q184671


The information in this article applies to:


SYMPTOMS

In Microsoft Project 98, when you level a project, an unexpected delay may occur on tasks with Start No Earlier Than (SNET) constraints.


CAUSE

This behavior occurs when a task has a SNET constraint that is during nonworking time. The leveling delay added to the task includes the nonworking time, which adds more delay to the task than is necessary.


WORKAROUND

To work around this behavior, avoid assigning a task a SNET constraint during nonworking time. Instead, assign SNET constraints during working time.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

ARTICLE-ID: Q185102
TITLE : PRJ98: How to Obtain and Install MS Project 98 SR-1

Additional query words:


Keywords          : kbdta projwin 
Version           : WINDOWS:98
Platform          : WINDOWS 
Issue type        : kbbug 

Last Reviewed: July 14, 1999