SYMPTOMS

In Microsoft Project 98, when you update percent complete for a task, all percent complete values and BCWP values may appear in the first time period of the Task Usage view.


CAUSE

This behavior occurs when all of the following conditions are true:

NOTE: To change the "Updating task status updates resource status" option, follow these steps:

  1. On the Tools menu, click Options.


  2. In the Options dialog box, click the Calculation tab.


  3. Click to clear the Updating task status updates resource status check box. Click OK.



RESOLUTION

To correct this behavior, install Microsoft Project 98 for Windows, Service Release 1 (SR-1).


STATUS

Microsoft has confirmed this to be a problem in the Microsoft products listed at the beginning of this article.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).


For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

Q185102 PRJ98: How to Obtain and Install MS Project 98 SR-1